Hamley Bridge Pipeline Upgrade: Delivering Infrastructure with Impact
Fleurieu Civil & Construction was engaged by SA Water to undertake a major infrastructure upgrade in Hamley Bridge, involving the installation of a new water main and associated works. The project showcased the team's capability to deliver high-quality outcomes in remote environments while maintaining environmental and safety standards.
Project Scope
The construction works included:
Installation of 981 metres of DN300 DICL pipe (ductile iron cement lined)
Installation of 48 metres of DN100 DICL
Installation of 3 stop valve assemblies
Installation of 6 additional stop valve assemblies
Installation of 3 fire plugs
Development of a new service road
Road reinstatement after excavation
Full system flush, including chlorination and commissioning
Environmental Considerations
Throughout the project, local vegetation was carefully managed in accordance with environmental best practices. The team ensured minimal disruption to the surrounding ecosystem while delivering essential upgrades to water infrastructure.
Results That Matter
This project was:
Delivered on time
Delivered within budget
Completed with zero safety incidents
A fantastic achievement by the team, especially given the challenges of working in a remote regional setting. This project stands as a testament to Fleurieu Civil & Construction’s commitment to quality, safety, and environmental responsibility.