Strategic water storage upgrade

Our team played a pivotal role in upgrading critical potable water infrastructure through the full replacement of a legacy dam with new high-capacity storage tanks. The project demonstrated multidisciplinary delivery across civil, structural, mechanical, piping and electrical systems.

Scope of works included:

  • Demolition and decommissioning of a 10ML potable water dam.

  • Construction and installation of three 5ML steel storage tanks.

  • Tie-in of tanks to existing inlet and outlet infrastructure.

  • Full integration of civil, mechanical and electrical systems.

  • Final commissioning and handover.

Delivered over a 20-month period, the project met all quality and safety benchmarks, coordinated multiple trade disciplines under a unified structure, and ensured uninterrupted access to water throughout the transition.